When you have finished using the Standard Time Project Integration Wizard, you will see a list of tasks in the Project Tasks view. Each task will correspond to those in the Microsoft Project plan.
1) Choose View, Project Tasks. The view below will be displayed.

2) There are many ways to track time to a project task. You can right-click on the task and choose Start or any of the many other time tracking choices. If a task is marked as a Quick Task it will show up in the Timesheet, Quick Task window, and will be synchronized with your PDA.
Standard Time links the following fields to Microsoft Project fields:
| Standard Time field |
Microsoft Project field |
Description |
| Name |
Task Name |
Name of the task |
| Duration |
Duration |
Forecasted duration (in hours) |
| Remaining |
Remaining Work |
Hours left to work |
| Actual Work |
Actual Work |
Hours worked |
| Percent Complete |
% Complete |
Percentage of work performed |
| Users |
Resources |
Employees assigned to task |
|